I&R Demolition was awarded the contract for demolition and site clearance at the Church Road Centre in St Anne’s to make way for 10 new properties on the site.
The demolition and site clearance consisted of a 6 week program including crushing the hardcore on site and creating a piling mat once the site clearance was complete.
Site levels had to be reduced which involved removing 1500 ton of sand which was the make up of the ground under the existing building then putting down a 600mm piling mat of 6F2 ready for the piling rig.